Innovation / Applied research
From model
to experiment.
Try the assembly sequence for a station bay. Then match three field reports to a model and see what happens when a revision or an identifier changes.
4D assembly sequence
Each activity belongs to a group of components. Change the phase or the view to inspect the assembly order and its dependencies.
How to read the sequence
- Component and activity
- Select “Deck”. The girders and platform appear in coral. The piers carrying their loads are already shown in place.
- Two views, one phase
- The axonometric view separates the two lines of supports. The elevation projects grid lines A and B onto one plane, revealing the continuity of the span.
- Scope of the demonstration
- The geometry and assembly sequence were created for this study. Quantities refer to this example. A project schedule also needs production rates, temporary works and contractor review.
Data integration
Which part does this report belong to?
Report F-018 records an inspection of a longitudinal girder. Switch scenarios to check whether the element and revision it references allow the observation to be linked to the model.
Field report
F-018Reported reference
GIR-02 · R07
Model element
GIR-02Longitudinal girder · R07
Identifier GIR-02 exists in the inventory and both revisions are R07. The report can be linked to the girder.
| Report | Reference · revision | Result |
|---|---|---|
| F-017 | COL-A1 · R07 | Linked |
| F-018 | GIR-02 · R07 | Linked |
| F-019 | FRM-03 · R07 | Linked |
Digital engineering
Follow one component through the model.
Take the synthetic pavilion into the engineering viewer. Select a member and compare the information that describes its shape with the planning and cost assumptions assigned to the exercise.
- Evidence
- The IFC component record supplies the class and geometry available in this sample.
- Intervention
- Change the reading mode and trace how the selected component relates to sequence and quantities.
- Output
- A component-level record. The example costs and dates are assumptions for the exercise.
Research questions
What would a pilot need?
Three questions we could test with a defined scope and an agreed evaluation criterion.
- AI for issue triage
- Could it suggest the discipline responsible? We would need anonymised issues labelled by specialists. We would compare suggestions against those labels and examine incorrect assignments.Synthetic example: route a fictional duct clearance issue to a reviewer and let them correct the proposed assignment.
- Spatial review in XR
- Is the access route to a piece of equipment easier to understand? A trial would need a model extract with a verified scale and a specific inspection task. We would record where users lose their bearings.Synthetic example: use a virtual plant room to test whether a person can locate an isolation valve.
- Data for a digital twin
- What happens when a reading arrives late? A stable identifier, units and timestamps would let us test that case and check whether the viewer distinguishes the latest valid value.Synthetic example: delay one invented temperature reading and check how its timestamp is presented.